905 799 0900 | Guruvayurappan Temple of Brampton gtbrampton@yahoo.ca

Construction updates

Updated: 15 January 2017

  • Roof decking is completed and the roof finishing works has started
  • External windows have been installed
  • The shelf angle and blue skin works ongoing with the brick work commencing next week
  • The basement framing is completed along with rough-ins
  • Brampton hydro has been working on site to pull their primary cables and would be installing their transformer

Updated: 11 December 2016

  • The steel stud framing around the building is complete
  • The roof deck and external walls are nearing completion. Expected completion by December 15
  • The foundations for the Sreekovils, Valliambalam , along with the floor slab concrete is complete
  • The basement works are progressing rapidly with rough-ins for the washrooms and other areas inside basement completed
  • Equipment like boiler, storage tank have been installed and HVAC equipment is on site
  • Sprinkler lines, HVAC ducting and electrical works are progressing in the main hall
  • Externally, the concrete curbs and basecoat of the asphalt has been completed
  • The electrical duct banks and service connections are completed

Updated: 18 November 2016

  • Dry wall being erected
  • Floor is cemented
  • Curbs on temple ground and parking lot
Share This