905 799 0900 | Guruvayurappan Temple of Brampton gtbrampton@yahoo.ca

Construction updates

GTB Construction Progress as of August 12, 2016.

  • Roof truss erection works all of the 8 gables completed
  • Roof extensions(slope down) on all sides except east side completed
  • Purlins tie members interconnecting each truss commenced starting from ridge on west side
  • Basement exterior walls completed
  • Basement inner partition wall and main RCC column completed
  • Elevator shaft work within basement completed
  • Soil backfilling/compaction inside the main shell on north side abuting basement wall in progress
  • Overall granular B placing/compaction on east side,south side and west side in progress and this seem to ease construction traffic around the structure

Images taken in June, July 2016

As of end of June 2016, the progress of construction works for the temple is as follows-

1. The steel structure erection for the temple building has commenced. Steel columns are being erected now and it is anticipated that the entire steel structure would be completed in 4 to 6 weeks.
2. The basement walls are completed along with the underground water and sewage lines below the basement slab.
3. The main municipal water and sewage lines are connected to the building now.
4. The external roads and parking lot is being levelled and built up to receive asphalt.
5. The internal finishes along with other architectural elements have been approved.
6. The permit application for the internal sreekovil stuctures are being reviewed by the City of Brampton.

Ground Breaking

It is with extreme pleasure I let all of you know that we have achieved another milestone on our Temple project. The Board has issued the letter of intent for Phase 1 of the project to the lowest bidder Everstrong Construction Limited after due review and background...

Letter of intent issued

It is with extreme pleasure I let all of you know that we have achieved another milestone on our Temple project. The Board has issued the letter of intent for Phase 1 of the project to the lowest bidder Everstrong Construction Limited after due review and background...

Building permit received

Dear Devotees, friends and all supporters and well wishers of the Guruvayurappan Temple of Brampton, I am delighted to inform you that on 12th August 2015 we received the long awaited Building Permit from the City of Brampton. (Building Permit #15 106 671 P01 00 IS)...

Building Fund Raising – President’s Update

BUILDING CONSTRUCTION FUND: (Target) $2.5 Million CURRENT ASSETS OF THE TEMPLE INCLUDING LAND AND CAPITALISED EXPENDITURE: $2.5 Million LOAN PLEDGES ( including cheques received and to be received- mostly for 4% interest; some interest free and a small portion as...

Share This